The first stage of major improvements to the Lansdowne area will commence on 15 March 2021.
This initial phase will require Holdenhurst Road, between Lansdowne Roundabout and Station Roundabout, to be closed to vehicles for approximately 12 weeks. A diversion will be in place via St Swithun’s Road and Christchurch Road.
Access for people walking and cycling along Holdenhurst Road will be maintained, with efforts made to ensure that businesses can continue their operations with minimal disruption.
If any of our levy payers have any queries while the works are taking place, they can contact lansdowne@balfourbeatty.com between 9am and 4pm Monday to Friday.
Read the BCP Council press release here
Read more about BCP Vision for Lansdowne
Phase 1: 15 March for up to 7 weeks – Lansdowne Roundabout to the Fire Station Square
The work will require the closure of Holdenhurst Road between Lansdowne Roundabout and Fire Station Square for the duration (see map). Holdenhurst Road will be open for access only (no through route) between Cotlands Road and Station Roundabout so that deliveries can be taken as usual. Pedestrian access will be maintained throughout. There will be a signed vehicle diversion route for other traffic via St Swithuns Road.
Phase 2: 3 May for up to 12 weeks – The Fire Station Square to the junction with Cotlands Road
The work will require the closure of Holdenhurst Road between Fire Station Square and just north of Cotlands Road for the duration (see map). Holdenhurst Road will be open for access only (no through route) between Cotlands Road and Station Roundabout, and at the Lansdowne Roundabout end so that deliveries can be taken as usual. Pedestrian access will be maintained throughout. There will be a signed vehicle diversion route for other traffic via St Swithuns Road.
Phases 3 and 4 are yet to be finalised.
Bus stops along Holdenhurst Road will be temporarily closed or relocated during these works.